Wednesday, December 21, 2011

Maintenance Drainage 2011



December 2011improvements
200 metres of Field Drains at the lower camp, included :-
60 tons of 40 ml graded aggregate,  200 metres of trenches,
a 2 cubic metre soakaway
3 men and a few cups of tea.

Plus machines:-A Dumper truck


Large and small digger


With assorted buckets and fork attatchments 
 for trenching and removing old scrap metal from near the badger hide.

New pitch after removal of rubbish

New path on top of drainage channels